March 11, 2025 - Project Update

Work underway includes replacing the existing manhole, quality control testing, and tying the new pipe into the existing sanitary mains on Craig Drive and Graham Avenue.

To complete this work, the Craig Drive and Graham Avenue intersection are now closed and will be for the next couple of weeks. The intersection is now local access only.

Traffic is being rerouted through Apple Street and Mills Avenue.

The contractor will install new road gravels and paving will take place in early spring.